Step-by-Step FESCO Net Metering Guide (Requirements & Timelines)
Net Metering

Step-by-Step FESCO Net Metering Guide (Requirements & Timelines)

By SheikhX Engineering

Pre-requisite: The 3-Phase Meter

To qualify for net metering, your house must already have a FESCO 3-Phase meter. If you have a single phase, you must upgrade it first.

The Real Timeline

The standard process involves several regulatory hurdles:

  • FESCO SDO Audit: They inspect your setup for proper earthing and breaker compliance.
  • NEPRA License: NEPRA issues the actual Generation License. This takes the longest (4 to 6 weeks).
  • Demand Notice & Installation: Once the license is granted, you pay the FESCO demand notice, and the Green Meter is installed.

The realistic total timeline is 2.5 to 3 months from installation to FESCO meter activation. At SheikhX Solar, we handle this entire bureaucratic process transparently so you don't have to visit a single office.